List of steps
(Total number of steps: 5)
Obtain petrol service station construction permit  (5)

Preview & Print

Properties
 
Summary of the procedure
 

Where to go? (1)

You will have to go to the following agencies. The number indicates how many interactions are required with each entity.
Energy Regulatory Commission (x 4)
1 2 3 5
Energy Regulatory Commission

What you will get (1)

The objective of the procedure is to obtain those documents.
Petrol service station construction permit
5
Petrol service station construction permit

Required documents 

The documents with green band will be provided to you during the procedure.

Certificate of incorporation
1
Certificate of incorporation
Identity card (x 2)
1 5
Identity card
Proof of land ownership
1
Proof of land ownership
Notification of approval of development permission
1
Environmental Impact Assessment license
1
Environmental Impact Assessment license
Approval of construction of an acceleration and deceleration lane
1
Approval of construction of an acceleration and deceleration lane
Mechanical engineer's drawwing
1
Mechanical engineer's drawwing
Civil engineer’s drawings
1

How much?

Free of charge

How long ?

The estimated total time is calculated by adding the time spent: 1) waiting in queue, 2) at the counter and 3) between steps.
  Min. Max.
Total time (sum): 4 d 45 d
of which:
Waiting time in queue (sum): 10mn 20mn
Attention at counter: 1h. 20mn 2h. 45mn
Waiting time until next step (sum): 4 d 45 d