List of steps
(Total number of steps: 7)
Obtain electricity generation, distribution and supply licence  (7)

Preview & Print

Properties
 
Summary of the procedure
 

Where to go? (2)

You will have to go to the following agencies. The number indicates how many interactions are required with each entity.
Kenya Commercial Bank
3
Kenya Commercial Bank
Energy Regulatory Commission (x 4)
4 5 6 7
Energy Regulatory Commission

What you will get (1)

The objective of the procedure is to obtain those documents.
Electricity generation licence
7

Required documents 

The documents with green band will be provided to you during the procedure.

Environmental Impact Assessment license (x 2)
1 4
Environmental Impact Assessment license
Engineer's report (x 2)
1 4
Route sketch (x 2)
1 4
Route sketch
Certificate of compliance with the physical planning act (x 2)
1 4
Certificate of compliance with the physical planning act
Newspaper advertisement (x 2)
1 4
Audited accounts (x 2)
1 4
Audited accounts
End user tariff (x 2)
1 4
Electricity supply contract (x 2)
1 4
Customer service charter (x 2)
1 4
Complaint handling procedure (x 2)
1 4
Printed application
4
Application forwarding letter
4
Bank deposit slip
4
Bank deposit slip
Inspection checklist
6

How much?

Cost of the procedure  KES  10,000

Cost detail

Estimate your cost

KES 10,000
For licence application

How long ?

The estimated total time is calculated by adding the time spent: 1) waiting in queue, 2) at the counter and 3) between steps.
  Min. Max.
Total time (sum): 12 d 90 d
of which:
Waiting time in queue (sum): 5mn 30mn
Attention at counter: 40mn 2h.
Waiting time until next step (sum): 12 d 90 d

Legal justification?

The regulations which justify the procedure and its content
Energy (Licensing) Regulations, 2012 Energy (Licensing) Regulations, 2012
  articles 5, 16, 17, Reg 15, Reg 4, Reg 6
Energy Act Energy Act
  Sections 27, 28, 30, 31, 63
Kenya National Distribution Grid Code Kenya National Distribution Grid Code
Kenya National Transmission Grid Code Kenya National Transmission Grid Code
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License